Street Gantt - Oct

The third round of asphalt street repair starts Monday, October 20th for streets in International Subdivision. The cross streets of Scott, Audubon, Larose and Austin will be completely excavated and new full depth pavement restored. Work will begin on Scott Street, and then progress to Audubon, Larose, and Austin Streets through October and November. The contractor will notify emergency services and the school bus depot of the construction. As each street is being improved, there will be some limited access; crews will work as quickly as possible to keep driveways accessible during the construction. Please be careful around the construction crews.